What To Expect During Upcoming Construction Seasons:

2020 Construction Season (Spring 2020 – Fall 2020)

 

  • Between 28th Street and 31st Street:

Construction includes pavement reconstruction, sidewalks, driveways, water main, sanitary sewer, storm sewer, retaining walls, traffic signal replacement at 29th Street, and streetscaping. 

  • Between 31st Street and 34th Street (West Side):

Construction includes replacement of sidewalk, driveways, parking lots, and streetscaping. 

  • ​CEMAR Trail extension from B Avenue at 29th Street NE to Cedar Rapids City Limit near Mount Calvary Cemetary:

Construction includes the extension of the CEMAR Trail and includes an underpass between 30th Street and 31st Street.

 

2021 Construction Season (Spring 2021 – Fall 2021)

 

  • Between 27th Street and 28th Street:

Construction includes 27th Street intersection realignment, pavement reconstruction, water main, sidewalks, driveways, and streetscaping. 

  • Between 31st Street and 34th Street (East Side):

Construction includes replacement of sidewalk, driveways, parking lots, water main, sanitary sewer, storm sewer, traffic signal replacement at 32nd Street, and streetscaping.

The schedule remains subject to change. CLICK HERE to receive project updates as more information becomes available.

Completed:

Work completed to date includes primarily the underground utility and pavement improvements:

 

  • Utilities: Relocating and installing sanitary sewer, storm sewer, water main, and private utility lines. Also included burying electrical and cable utilities.

  • Pavement: Pavement rehabilitation, intersection realignment, and new curb and gutter. 

Street utilities work between 34th Street and 40th Street (COMPLETED FALL 2015)

This work included water main and sanitary sewer work.

 

Street rehabilitation between 34th Street and 40th Street (COMPLETED FALL 2016)

The contractor selected for this phase began work in 2015 with storm sewer construction. The work continues and is anticipated to be complete Fall 2016 and will include roadway improvements, pavement rehabilitation, and some sidewalk and corner radius improvements.

 

Street utilities work between 27th Street to 29th Street and 31st Street to 34th Street (COMPLETED FALL 2016)

This work included water main and sanitary sewer work.

Street rehabilitation between 27th Street and 34th Street (COMPLETED FALL 2017)

This work included pavement rehabilitation, storm sewer work, and sidewalk and corner radius improvements.

Sidewalk work between 34th Street and 40th Street (COMPLETED FALL 2018)              

This work included replacing and/or modifying the sidewalk, driveways, and parking lots. 

 

Street Reconstruction at 38th Street (COMPLETED FALL 2018)

This work included the realignment of 38th Street as well as the replacement of the traffic signals. 

 

Street Reconstruction at 40th Street (COMPLETED FALL 2018)

This work included the realignment of 40th Street as well as the replacement of the traffic signals.

No construction was conducted in 2019 Construction Season 

 

 

STAY CONNECTED

CURRENT STEP

FINAL DESIGN/CONSTRUCTION

CLICK HERE TO LEARN MORE